Owner : | Deutsche Bahn Netz AG |
General contractor : | Alpine |
Consultant : | ILF |
Application : | Face stabilisation TBM exit portal |
FiReP Solution : | temporary rockbolting |
Construction date : | 2011-2012 |
Products : | K60-32 GRP Powerthread® solid rock bolt L = 10.0m |
General information : | In the area of critical ground conditions above the tunnel portal and in the tunnel face 10.0m long FiReP® GRP Powerthread solid bolts were installed. Due to the very good cuttablility properties of the FiReP® GFRP the TBM can easily cut through this last with GRP bolts reinforced rock section. High working loads on anchor head (>500 kN) are achieved by installing two steel nuts in a row. |
Jobsite Photos |
![]() |
![]() |