Reference‎ > ‎

Downtown Line Stage 2; C912

Owner : Land Transport Authority 
General contractor : Lum Chang Buildings Contractors Pte Ltd
Application : Soft-Eye
FiReP Solution : GRP mesh, GRP bolts
Construction date : 1. 03/2010     2. 07/2010
TBM information :
Products : 1. FiReP Rebar straight d=40mm
     FiReP Rebar Double Loop d=32mm
2. FiReP Rebar straight d=40mm, d=32mm, d=22mm
     FiReP Rebar stirrup d=32mm, d=22mm, d=16mm

General information : 1. Petir Station:
    2 TBM break-through
    FRP reinforced bore pile
2. Zone 6
    2 TBM break-through
    FRP reinforced bore piles